The NuraNet Windows software, tab by tab and menu by menu
18 sections: from the first connection to the inverters to the end-of-month financial report, with a picture of every screen and a complete reference of the seven menus at the top of the window.
The marks beside each section title:Beginner means you need it to get started, Everyday user means the operator's daily work, Advanced means you can skip it for now and come back later. If you are new, read only the green sections; you can monitor your plant today.
1Installation, licence and first runBeginner
The software is installed on the plant's own computer, not on a personal laptop. The reason is simple: the program reads the inverters directly over the RS485 cable or the local network, so it has to be where the cable is.
Run the installerThe installer is encrypted and locked to that computer's hardware. If the computer is replaced, the licence has to be issued again.
Enter the licenceThe code we gave you at handover. Without it the program does not run.
Sign inOn first run, sign in as the Admin user. The window's title bar always tells you which user you are signed in as: ... | admin (Admin).
Check the minimum requirementsHelp › Minimum Requirements — if the computer is weaker than this, the program runs but the charts become slow.
Consider unattended modeAccess › Unattended Operation — if the plant has no permanent operator, turn this on so that after a power cut the computer starts by itself and resumes monitoring.
Automatic updates. New versions are signed, and the program fetches and installs them by itself. You don't need to download anything by hand, and an unsigned package is not installed.
2The window at a glanceBeginner
Every time you open the program you see this same layout: a menu bar, a status bar and six tabs. If you read only this section, the rest of the program becomes guessable.
The main window — status bar, tabs and the Overview screen
The status bar — six boxes at the top of the screen
These six boxes are the same in every tab. Every morning, read just this one bar.
Total Power — instantaneous power against rated capacity, e.g. "2261 kW / 3909 kW". The ratio tells you what percentage of its capacity the plant is delivering.
Online — how many inverters out of how many are responding. "33/35" means two are silent. This is the most important number on the screen.
Error & Alarm — the number of real errors and alarms reported by the devices themselves. When it is not zero, the box frame turns red.
AI Alarm — the number of AI findings. Separate from the previous box, because they are a different kind of thing.
Efficiency (PR) — the whole plant's efficiency. If it shows "--", there is not yet enough data to calculate it — it does not mean zero.
Modbus Status — the state of the communication line to the inverters. If it says Disconnect, no new figures come in, and the rest of the screen is the last thing we knew.
Six tabs
Tab
What for
Overview
Today's status on one screen: energy, power trend, weather, forecast.
Plant Layout
A map of the plant's structure — locations, transformers, substations. For understanding "where".
Solar AI
Intelligent analysis: anomalies, prioritisation and suggested actions.
Maintenance
Jobs to be done, sorted by the energy being lost.
Energy Hub
Energy flow between sun, grid, diesel and load.
Power Quality
Power quality: harmonics, unbalance, frequency, standards compliance.
3Connecting to the invertersBeginner
Until this is done, no figure enters the program. It is the first thing you do at installation and the first place you return to when troubleshooting.
Open Run › Connection Setting
Enter the port (COM or network), baud rate, response timeout and the range of inverter numbers to match what is set in the inverters.
Check the wiringOn RS485, swapping wires A and B is the most common mistake; its sign is that no inverter responds — not just some.
Press StartFrom Run › Start. The Modbus Status box should go from Disconnect to connected.
See the result in All InvertersView › All inverter — inverters that have responded show figures, and the rest stay at zero.
If some inverters respond and some don't, the problem is not the connection settings — the settings are either right for all of them or for none. Look at a duplicate address (Slave ID), the end of the RS485 line, or the power of those inverters themselves.
Remember to press Start again after Stop. While monitoring is stopped, no data is written to the archive, and later you will have a hole in the reports.
4The Overview tabBeginner
The screen that is in front of the operator most of the time. It has three columns.
The Overview tab — energy, trend, weather and the row of inverters
Right column — the Energy Metering panel
Today Working — today's operating hours.
Year / Month / Week Energy — energy for the year, month and week. If a period is incomplete it says plainly how many days are missing ("25 of 30 days missing") instead of giving a small, misleading number.
Today So Far — today's measured energy up to this moment.
Today Forecast — the AI's forecast for the whole of today. Don't confuse it with the line above.
3-Day / 7-Day / 30-Day / 1-Year Forecast — longer-range forecasts, for planning and revenue estimates.
Middle column — the charts
Total Grid Power Trend — above the chart there is a number and a unit (e.g. "10" and "Days") that set the period, together with the time of the last update and the inverters' daily energy.
Drag-Zoom and Reset — with Drag-Zoom, draw a box on the chart to enlarge that period; Reset brings it back. To see a drop lasting a few minutes, this is the only way.
The bar chart at the top — daily energy, with three figures below it: best day, 30-day revenue and today's revenue.
The gauge — efficiency (PR) as a percentage, on a red-to-green scale.
The large chart at the bottom — the total power curve. Hold the pointer over any point and the exact time and value are written right there.
Left column — grid, weather and map
Grid status, current weather (temperature, humidity, wind, sky conditions), the forecast for today/tonight/tomorrow, a map of the plant's location, and sunrise and sunset times. Sunrise and sunset are not just decoration: NuraNet uses them so it does not count the shutdown after sunset as an error.
The row of inverters — at the bottom of the screen
For each inverter, a pair of buttons: a blue panel-shaped rectangle on top and a numbered square below.
Numbered square — click it to open that inverter's detail window. Its colour is that inverter's status: green normal, yellow stopped, red error, blue AI finding.
The blue rectangle above the number — opens that inverter's panel/MPPT layout directly, without first going into the inverter screen.
5The Plant Layout tabEveryday user
This tab answers "where". Overview says the plant is delivering 2261 kilowatts; Plant Layout says which corner of the site is falling short.
The Plant Layout tab — locations, transformers and substation
Each location's box — the name, "Inv:3 Online:3", that location's instantaneous power and today's energy, and below it the numbers of its inverters in their status colours. One red number among the greens means the problem is right there.
Transformers — each transformer says how many inverters and how many locations are under it, and how much power and energy has passed through it.
Coloured lines — the path of energy from location to transformer and from transformer to substation.
GRID SUBSTATION — today's power and energy at the delivery point, with today's and last month's revenue.
The side column — the same Energy Metering panel and weather as in Overview, so you don't have to go back and forth to see them.
Why this tab is really useful: when three inverters in one location drop together, the problem is almost never the three inverters — it is something the three have in common: one transformer, one cable route, or the shadow of one building. This view shows exactly that shared thing.
6The Solar AI tabEveryday user
In Overview you see that production is low; in Solar AI you see why and how much. The AI answers one question: what took how many kilowatt-hours from this plant, and who has to do what? The plant itself is its irradiance sensor: the inverters are compared at every moment with each other and with their own usual share, so cloud and dust drop out.
An error or alarm reported by the inverter itself always comes first, and the AI neither rejects nor delays it. AI findings are of four kinds:
Broken now — a plant at zero with the sun high, an inverter standing still while the others produce, a dead, cut or short-circuited string or input, low insulation. It shows colour as long as it is true today.
Loss ledger — an inverter below its own usual share or its same-model neighbours, a weak input; each with kilowatt-hours per day.
Configuration — capacity, wiring or a disabled input that the measurements contradict; it has its own filter and is decided only in strong light.
Known — a problem that has stayed open for two weeks; it stays on the list but no longer colours the plant.
Each finding has an importance (very important, important, normal, low), and the Details button shows the evidence, the loss figure and the specific action for that type of finding. The AI scorecard button tells you what the program said and how each one ended.
When it stays silent: a live problem is reported only after three consecutive reading cycles; the shutdown after sunset and a monitoring outage are not failures; anything whose cost is trivial is not said; and something that hits a large part of the plant at once is said once for the whole plant. A finding that went away by itself quickly makes that type of finding stricter in this plant.
An important point about trusting this tab: if the plant's rated capacity or the ticks of the wired inputs are wrong, PR, the forecast and the loss ledger are all measured against a wrong number. Before you doubt the findings, check the capacity and the inputs once — the "Configuration" findings exist exactly for that.
Thresholds are set from Design › AI Alarm center, and a summary of the findings is seen in View › AI Alarm Summary. The same findings, with the same colour and the same sentence, are in the app and on the company site too. The full explanation of how the AI works ›
7The Maintenance tabEveryday user
This is where diagnosis turns into work. The job list is sorted by energy lost, not by time of entry — so the first row is your plant's most expensive problem.
The Maintenance tab — health, open jobs and the prioritised list
The top bar — health, warning and critical counters, environmental status, and AI counters (open / critical / overdue). Beside it four buttons: alarm center, reset all, refresh and export report.
Four sub-tabs — Today today's jobs, Jobs the full list, Schedule periodic maintenance (PM), History completed jobs.
Four indicator cards — plant health (%), needing attention, open tasks, and estimated losses (kWh per day). The last card is what the problem is taking from your pocket.
Each job's card — a severity label (CRITICAL), a status label (overdue), the problem title, a second line with the exact location and numeric evidence, and a third line with the suggested action. On the left, that item's estimated loss and the Done button.
The work cycle we recommend
In the morning, the "Today" sub-tabRead the first three or four items. You don't need to look at all 171.
Read the evidence in the card itselfThe card says which inverter, which string, what current against what median. You don't need to look for proof anywhere else.
Deal with it in the fieldThe suggested action is exactly what the technician needs to do.
Press "Done"The job moves to history and leaves the open list. If you don't press it, the same item will be at the top of the list again tomorrow.
Take an "export report" monthlyA document showing what work was done and how much energy was saved — for the employer or for the warranty file.
8The Energy Hub tabAdvanced
This tab is for plants that do not only deliver to the grid: a factory that consumes at the same time, has a diesel generator, or sells its surplus to the grid.
The Energy Hub tab — energy flow and self-consumption indicators
Five nodes — Solar, Grid, Load, Diesel and Export, each with its instantaneous power. The direction of flow between nodes shows where energy is going from and to.
Six tiles at the bottom — Self-Consumption (what share of your own production was consumed), Self-Sufficiency (what share of your consumption came from the sun), today's import and export, CO₂ saved and estimated savings in rials.
Three charts on the left — daily energy for the last 30 days, today's load profile, and power factor over 24 hours.
The top bar — the instantaneous power of all four sources in one place.
If your plant only delivers to the grid and has no consumption meter, this tab stays empty — and that is not a fault. Filling it needs a power meter or power analyzer on the load side. Each device has its own role: solar output, load, grid, diesel, main incomer, export meter or sub-meter. The software reads up to eight devices on the same bus.
9The Power Quality tabAdvanced
The quality of the electricity you deliver to the grid. This tab becomes important when the utility raises an objection or issues a penalty — and it is better to have looked at it before that.
The Power Quality tab — indicators, phasor, harmonics and standards compliance
Nine tiles at the top — voltage unbalance, voltage THD, current THD, power factor, frequency and peak current of each of the three phases.
Standards Compliance — compliance with IEEE 519 (TDD), class and flicker, with the Isc/IL ratio that the allowed limit is calculated from.
Grid Code — the reference grid code (e.g. VDE-AR-N 4105) and the status of power factor, frequency, voltage and power limitation against it.
Phasor Diagram — the voltage and current vectors of the three phases. The most visual way to see whether a phase has dropped out or its angle is wrong.
Harmonic Spectrum — the harmonic spectrum, with phase selection.
PQ Events — the last 200 power-quality events with time, type, severity and value.
EN 50160 Compliance — the four criteria of the European voltage and frequency standard, with the compliance percentage.
This tab needs a power-quality analyzer defined in Design › Power Analyzer Configuration. Without it, the tiles show dashes. The standards behind these calculations ›
10The All Inverters windowBeginner
From View › All inverter. The whole inverter fleet on one screen — the fastest way to find out which one has fallen behind.
The All Inverters window — one card per inverter
Each card has the inverter's number and type, a fill bar showing current power as a share of capacity, a status label and three lines of figures:
Input — DC input power from the panels, against input capacity.
Output — AC output power, against rated capacity.
Daily — today's energy for that inverter.
How to read it in two seconds: don't look at the numbers, look at the height of the bars. In a healthy plant they are all the same height. A card whose bar is empty or shorter than the others is the one to open — with a single click on the card itself.
Inverters of different capacity (say one 50 kW among 120 kW units) naturally show smaller figures; because the bar fills relative to its own capacity, they are still comparable.
11A single inverter's window — five tabsEveryday user
Clicking any inverter (from Overview, Plant Layout, All Inverters, or the menu View › All inverter › Inverter #n) opens this window. It has five tabs.
The Inverter Status tab
Inverter Status — input, output, diagnostics and trend
System Status — inverter selection, operating status and the time of the last update.
Input Data — two sub-tabs: MPPT Input Data (voltage, current and power of each MPPT) and String Input Data (the same, per string).
Grid Output Data — voltage, current and frequency of each of the three phases R/S/T, total grid power and power factor. If one of the three phases differs sharply from the other two, the problem is on the AC side, not the panel side.
Diagnostic Information — daily/weekly/monthly/yearly/total energy, heatsink and module temperatures, operating mode, and four lines of DSP and ARM alarms and errors. This is where you read the device's real error code.
Historical Trends — that inverter's trend chart, with parameter and period selection, Drag-Zoom, Reset and an Export button.
The Error History tab
The history of that inverter's errors with the time they occurred. When an inverter has a problem "sometimes", the timing pattern of this list gives the answer: an error that repeats every day at noon is a thermal problem, not an electronic one.
The All Parameter tab
Every register the inverter reports, raw and complete. It is not the first place for troubleshooting; it is the last, when you need to compare something with the manufacturer's manual.
The Inverter AI tab
AI analysis limited to that inverter — what you see in Solar AI for the whole plant, but only about this one.
The fifth tab, MPPT Layout, is so important that the next section is all its own.
12MPPT Layout and panel arrangementAdvanced
Two different things are done here together: seeing what each input delivers, and defining how many panels with what specifications are behind each input. The second is more important, because without it NuraNet does not know how much to expect from each string.
MPPT Layout — inputs, configuration and diagnostics
The MPPT Inputs row — for each input: voltage, current and power, with a panel icon. Below it three summary figures: average voltage, current and total MPPT power.
The configuration box — location, inverter type, rated power, number of MPPTs per inverter, number of strings per MPPT, number of panels per string, panel manufacturer and rated power, and panel dimensions and area.
Connected string inputs — ticks for the inputs that are really wired, with All and None buttons. An input with no wiring must not be ticked; otherwise NuraNet expects production from an empty input and raises a pointless warning.
Live bar and Apply button — instantaneous voltage, current, frequency and power; Apply saves configuration changes.
MPPT Trend — the trend of each MPPT parameter over any period.
Inverter Diagnostics — a table of time, severity, problem and recommendation. When there is no problem it says so plainly: "No issue detected".
Panel and string arrangement
Clicking any MPPT opens the panel arrangement window for that input.
Panel arrangement — each string's specifications and trend
Metric / String table — voltage, current and power of each string, and a "Connected" tick.
Panel specifications — number of panels in the string, rated power, manufacturer, dimensions, automatic area, and minimum and maximum tilt angle.
Panel Trend — the voltage or current trend of that string.
History / Issues / Recommendations — that string's record, with suggested actions.
Four buttons at the bottom — Apply To This MPPT this input only, Apply To All Same MPPT the same MPPT number on every inverter, Apply To This Inverter every input of this inverter. For a plant whose strings are all identical, the third button saves hours.
Fill this screen in carefully. The number of panels per string and the panel's rated power are inputs to the plant's capacity; capacity is an input to efficiency and the forecast; and the forecast is the basis of the AI warnings. One wrong number here shows up in four other places as a pointless warning.
13The Power Analyse windowAdvanced
From View › Power Analyzer. It does one thing: ranking. Instead of opening 35 inverters one by one, this window separates the best from the worst.
Power Analyse — ranking and the plant's full electrical table
Sort Tables By — the ranking criterion (e.g. current output power). Change it and all four boxes below are re-sorted.
Top 5 / Bottom 5 Inverters — the five best and the five weakest inverters. The second row is the one you will use.
Top 5 / Bottom 5 MPPT Inputs — the same, at input level. An MPPT at zero power among the rest means a lost string.
Full Plant Electrical Table — the full table: transformer, location, inverter, type and power, status, power and energy, and the voltage/current/power of each MPPT. Sortable and filterable, with an Export button.
Export All Top/Bottom — all rankings exported at once.
Power Analyse Trend — at the bottom of the same window
Power Analyse Trend — several inverters compared on one chart
Right there you can put several inverters together on one chart: scope, display mode (separate series or aggregated), parameter and period. The inverter-number ticks under the toolbar decide which ones are plotted.
Its main use: choose the "All MPPT Current" parameter with separate series. The lines that break away from the bundle are the strings you need to go to — without reading a single number.
14Energy financial reportEveryday user
You reach this window from the energy meter (View › Energy Meter). It answers "how much did we produce and earn this month" — on the Persian calendar and in rials.
Energy financial report — Persian-calendar period, indicators and a chart per inverter
Calendar — Persian solar, Gregorian or Hijri; start and end dates are written in that calendar.
Scope and Display — the scope (whole plant or per inverter) and display mode (separate or aggregated series).
The "Use AI forecast…" tick — for today and future days it uses the AI forecast instead of an incomplete figure. Turn it off for an official report; turn it on to estimate the current month.
Inverter ticks — All or a manual selection from #1 to the last inverter.
Eight result boxes — total energy, total revenue, revenue in million rials, daily average, number of active production days, best day, length of the selected period, and Archive Overlap.
Chart — daily energy, with one coloured bar for each inverter.
Report button — a presentable output of these results.
Be sure to read "Archive Overlap". This figure says what percentage of the period you selected actually has recorded data. If it is 43%, "total energy" also covers that 43%, not the whole month. NuraNet doesn't hide this, so you don't hand in a report you don't know is incomplete.
15Complete menu referenceEveryday user
The seven menus at the top of the window, with all their options. You will not see some options with your own user role — this is deliberate, not a bug.
The File menu
File tasks, printing and moving settings between two computers
Option
What it does
Print
Prints the current screen.
Full Screen
Makes the window full-screen — for the control room's wall monitor.
Export Settings
Saves the whole plant configuration to one file: layout, panel specifications, connection settings. Take one before every major change.
Import Settings
Restores that same file. For setting up a second computer or going back from a wrong change.
Export Data
Exports the recorded data.
Import Data
Imports archived data — for example after replacing the computer.
Export AI
The package of what the AI has learned about this plant.
Import AI
Puts that same package onto another installation, so a new plant doesn't start from zero.
Language Model
The optional language model: installation status, whether this computer has enough memory, and installation from a .nlm file (on a USB stick) or by download. The rest of the program works fully without it.
The Edit menu
The program's appearance, sound and language
Option
What it does
Theme Select
Chooses the program's colour theme.
Sound › Error Sound
The sound played on a real error.
Sound › Alarm Sound
The alarm sound. In a control room where nobody is always watching the monitor, set these two differently so you can tell which is which by sound.
Language
The user-interface language — Persian, English or Arabic.
The View menu
Display and report windows. They change nothing; they only show.
Option
What it does
All inverter
A submenu. Its first option opens the "All inverters" window, and after that there is a separate submenu for each inverter with its entries: Inverter status, MPPT layout, Panel layout, Error history, All Parameter and Inverter AI. The fastest way into the heart of a particular inverter.
AI Alarm Summary
A summary of the AI findings in one window.
Ask the Plant
Ask about the plant in plain language ("why is inverter 7 under-producing?"). The answer is built only from the plant's own data and checked figure by figure before it is shown. Needs the language model to be installed.
DC Array Diagnosis
Analyses each PV input from its dawn Voc and noon operating point: missing modules, bypass diodes, open parallel strings, voltage drop under load and the Voc trend. With a chart of the operating points beside the module datasheet curve. No command is sent to the inverter.
Energy Meter
The energy meter, and from there the energy financial report.
Power Analyzer
The Power Analyse window — ranking of the best and weakest inverters and MPPTs.
Standard Reports (IEC 61724)
Performance reports based on IEC 61724 — what you need to present to the employer or the insurer.
The Design menu
Configuration. This menu "defines" the plant, so access to it is restricted.
Option
What it does
Solar Plant Configuration
The backbone of everything: locations, transformers, the number and type of inverters, rated capacity. If these numbers are wrong, efficiency and the forecast are wrong too.
Power Analyzer Configuration
Define the power meters and power analyzers: the model, where the device sits in the plant, and the load it measures. Ready profiles for Schneider PM2220 and PM2230, Femto, Janitza UMG 96RM-E, Lovato DMG900, ABB B24 series and Baset Pajouh B851. Up to eight devices.
inverter page › All MPPTs
A view of every MPPT input in the whole plant on one screen.
inverter page › All Panel
A view of all panels/strings.
Efficiency center
The efficiency calculation center.
AI Alarm center
Where the AI warning thresholds are set — how much deviation counts as a "warning".
The Run menu
Starting and stopping reading from the inverters
Option
What it does
Start
Starts monitoring. From this moment the software keeps reading the inverters and writing to the archive.
Stop
Stops monitoring. While it is stopped no new data is recorded — remember to press Start again.
Connection Setting
Port, speed (baud rate), timeout and the inverter address range. The first place you go during installation and the last place you go when tracing a communication fault. On the Server tab, if NuraNet Link R is beside this computer, the backup option and the line-silence time are right there: ten minutes by default, from one to one hundred and twenty minutes.
The Access menu
Users and access. Part of this menu is visible only to Admin.
Option
What it does
Access Setting
The access matrix: which role sees which menu. Admin only.
User Management
Creating, editing and deleting users. Admin only.
Archive Setting
On which drive and with what policy data is kept.
Unattended Operation
Unattended mode: after a power cut the plant computer starts by itself, signs in by itself and resumes monitoring by itself. For a plant with no permanent operator.
Switch User
Switches user without closing the program — for shift handover.
Logout
Signs out.
The Help menu
The in-program guide and technical reference. All of it works offline.
Option
What it does
Start / Dashboard / AI
The guide's first three pages: quick start, dashboard introduction and an explanation of the AI.
Technical Documentation
Technical documentation.
Devices Management
Equipment management.
Installation & Configuration
Installation and configuration.
Troubleshooting
Troubleshooting.
FAQ
Frequently asked questions.
Security & Privacy
Security and privacy.
Tips & Tricks
Tips and tricks.
About / Minimum Requirements
The program version and the minimum hardware required.
Contact Me
Ways to contact us.
System Logs
System logs. When something isn't working properly, the evidence is here — and this is what to send us.
Inverter Reference
The inverter reference: every status code and every error code of each brand, and its NuraNet equivalent.
Power Analyzer Reference
The same reference, for power-quality analyzers.
16Users, roles and shiftsEveryday user
The software is built for a control room where several people work. There are two important decisions here.
Each role, its own menu
In Access › Access Setting (Admin only) you decide which parts each role sees. Our advice: the shift operator should not have access to Design. Plant configuration is not something needed mid-shift, and a mistake there produces weeks of false warnings.
Shift handover
Access › Switch User changes the user without closing the program — monitoring is not interrupted. It matters because maintenance work is then recorded in the name of the person who actually did it, not whoever opened the program in the morning.
A plant with no operator
Access › Unattended Operation is for a plant where nobody sits watching: after the power goes off and on, the computer starts by itself, signs in by itself and resumes monitoring. Without it, a half-hour power cut can turn into several days of missing data — and nobody notices until report time.
Take backups. Before any major configuration change, press File › Export Settings once. If something breaks, Import Settings brings everything back. Where data is kept is set from Access › Archive Setting.
17Everyday tasks, step by stepEveryday user
Start of shift — 2 minutes
The top status bar: Modbus Status must be connected and Online complete.
The Overview tab: does today's power curve have a normal shape?
Look at the Error & Alarm and AI Alarm boxes.
The Maintenance tab, "Today" sub-tab: read the first three items.
An inverter has gone offline
View › All inverter — find the card that is at zero.
Open it and read the DSP and ARM errors in Diagnostic Information.
The Error History tab: is this the first time, or is there a pattern?
If no error is recorded and it is just silent, it is a communication problem: the RS485 cable, the address, or the inverter's own power.
If it is after sunset, it is not a problem at all — the inverter switches off at night.
Efficiency has dropped but there is no error
Look at View › Power Analyzer and the Bottom 5 MPPT Inputs box.
Open the inverter whose weak input is there, MPPT Layout tab.
Compare that input's voltage and current with its neighbours: normal voltage and low current means shade or soiling; very low voltage means the string has opened.
Before drawing any conclusion, check the rated capacity in Design › Solar Plant Configuration — a wrong capacity makes efficiency wrong too.
End-of-month report
View › Energy Meter → energy financial report.
Persian calendar, the month's period, Scope on "whole plant", and untick the AI forecast.
Calculate Report, then read Archive Overlap; if it is well below 100%, the report is incomplete.
Report for the output. For the standard performance report, View › Standard Reports (IEC 61724).
Also take an "export report" from the Maintenance tab so the completed work is attached.
Setting up a new plant
Design › Solar Plant Configuration: locations, transformers, number and type of inverters, rated capacity.
Run › Connection Setting, then Start; confirm in All Inverters that all of them respond.
For one inverter, fill in the MPPT Layout tab completely: number of strings, number of panels, panel power and dimensions, and the ticks of the wired inputs.
Use Apply To This Inverter and then Apply To All Same MPPT to extend it to the rest.
Access › User Management: create the users and restrict access.
File › Export Settings: take a backup.
Access › Unattended Operation: if the plant has no permanent operator, turn it on.
18When something doesn't workBeginner
Symptom
First suspect
What to do
Modbus Status stays on Disconnect
Monitoring hasn't started or the port is wrong
Run › Start; if it still doesn't work, check the port and baud rate in Connection Setting.
No inverter responds
Wires A and B swapped, or the wrong port
Swap the two RS485 wires and press Start again. If all inverters are silent, the problem is general, not individual.
Some inverters don't respond
A duplicate address or the end of the line
Each inverter's Slave ID must be unique. Also check the line-termination resistor and the power supply of those inverters.
Efficiency (PR) shows a dash
There isn't enough data yet
It is calculated after a few hours of operation. If it stays like that for days, check the rated capacity in Design.
The AI gives many strange warnings
Incorrect configuration
Review the rated capacity, the number of panels per string and the ticks of the wired inputs. Thresholds are in Design › AI Alarm center.
The energy report gives a low figure
A hole in the archive
Read Archive Overlap. A low figure means monitoring was stopped during part of that period.
The program has become slow
A chart with a very long period
Shorten the period of the charts. The minimum specifications are in Help › Minimum Requirements.
I can't see a menu that is in this guide
Your user role isn't allowed it
It is deliberate. Sign in as Admin or ask the administrator to open access.
I want to know exactly what happened
—
Help › System Logs. Send us this log; it is the fastest way to an answer.
The in-program guide is always available too and works offline: Help › Troubleshooting and Help › FAQ. The error-code reference for each inverter brand is in Help › Inverter Reference.