What is a solar plant's performance ratio (PR), and how is it calculated per IEC 61724?
When you ask "is my plant working well?", the daily production figure is not an accurate answer: production depends on the sun, and a cloudy day always gives a lower number. The indicator that shows a plant's real health independently of the weather is the performance ratio (PR), defined in the international standard IEC 61724.
What is PR?
PR is the ratio of the energy actually produced to the energy that "in theory" should have been produced with the irradiance received:
PR = actual energy produced ÷ (irradiance received × the plant's rated capacity at STC)
Put simply: if the sun gave the equivalent of 5 full-sun hours today and your 1-megawatt plant produced 4.2 megawatt-hours instead of the ideal 5, today's PR is 84%.
What is a normal PR?
- 80 to 90 percent: a healthy, well-maintained plant
- 75 to 80 percent: acceptable, but worth investigating (soiled panels? high temperature?)
- Below 75 percent: an alarm bell — a serious loss whose root cause must be found
Note: PR is naturally a little lower in summer than in winter because of high cell temperature; comparisons should be made with a similar period.
Why does PR drop?
- Soiled panels — the most common cause in dusty climates; a loss of 3 to 8 percent is typical.
- Shading — plant growth, a new structure, or poorly designed row spacing.
- Inverter failure or derating — an inverter that limits power in the heat.
- String loss — a blown fuse, loose connector or faulty bypass diode that stays hidden for months.
- Ageing (degradation) — a natural decline of 0.5 to 0.8 percent a year; more than that means a panel quality problem.
The role of monitoring software
Calculating PR by hand is not practical: it needs simultaneous data from the irradiance meter, temperature and the production of every single inverter. Professional monitoring software calculates PR continuously and automatically, plots its trend, and warns when it drifts from the normal pattern. In performance guarantee contracts, too, the PR report based on IEC 61724 is the official document for arbitration between employer and contractor.
NuraNet calculates PR and the IEC 61724 standard reports automatically for every site.
Meet NuraNet